Tuesday - August 6th, 2019 - please expect delays as road crews start the traffic switch downtown at the FM 1093/FM 359 (Downtown) intersection. The switch will move traffic to driving on the new asphalt from James Lane to the intersection (FM 1093/FM 359). One lane of traffic each direction will be provided.
Law enforcement officers, directional signs, and message boards will be provided during the switch. Please have patience and stay alert!
Note:
The switch includes the detour.
James Lane residents will have access to revised roadway.
Lake Hill Farm Way / Fulbrook on FT:
- Lake Hill Farm Way residents will have to backtrack to Fulshear Trace for access to FM 1093.
- We (TxDOT) PLAN on having the curve at Fulshear Trace and adjacent portion of new FM 1093 eastbound open one week later – on/about 8/13.
- This will end the detour for Fulbrook residents.
- Lake Hill Farm residents will still have to backtrack while we continue to demo that section of old FM 1093.